The project information screen provides a summary of the most important information pertaining to a project / process. Can be displayed: "keyword", "id" (project / process ID), "indicator", "ID Number", "position", "Res" (resource ID), "demand", "resources", "status" , "Charge", "Is beginning", "end If", "initial plan", "end plan", "Start Date", "End Date", "Category" and "demand / Cumulative".
Matches the keyword assigned project / process. |
|
"ID" is the internally assigned identification of PLANOUT which is stored in the database |
|
In this field, a mark should be deposited in the form of an image |
|
The user-specified identification number of the project or process |
|
Specifies the location of the operations and projects. 1 - First project 1.1 - First task of project 1 1.2 - Second taskof project 1 etc. |
|
Represents the number of used resources, which is internally assigned of PLANOUT |
|
Displays the nominal capacity of the resource |
|
Shows the process used on the resources |
|
Der aktuelle Status den das Projekt trägt |
|
Indicates the person responsible for the projects / events. |
|
Here are the dates of the actual project progress displayed. |
|
Represents the data of the planned project progress. |
|
Displays the date the project started and the expected end. |
|
Shows as defined in the project / process the performanced Category. |
|
Has the same effect as "necessary", but here the need is added and result is written to the parent process and projects. |