Planning - The User Interface - The project table

Project information display

Vorherige Seite  Hauptseite  Nächste Seite Diese Seite drucken

 

The project information screen provides a summary of the most important information pertaining to a project / process. Can be displayed: "keyword", "id" (project / process ID), "indicator", "ID Number", "position", "Res" (resource ID), "demand", "resources", "status" , "Charge", "Is beginning", "end If", "initial plan", "end plan", "Start Date", "End Date", "Category" and "demand / Cumulative".

 

 

 

 

 

Project information display
Project information display

 

 

 

plan_gui_Stichw

plan_gui_x_stichwort_zoom50

Matches the keyword assigned project / process.

plan_gui_ID

"ID" is the internally assigned identification of PLANOUT which is stored in the database

plan_gui_Kennz

plan_gui_x_kennz_zoom50

In this field, a mark should be deposited in the form of an image

plan_gui_ID_NR

plan_gui_x_id_nr_zoom50

The user-specified identification number of the project or process

plan_gui_Position

Specifies the location of the operations and projects.

1 - First project

1.1 - First task of project 1

1.2 - Second taskof project 1

etc.

plan_gui_Res

Represents the number of used resources, which is internally assigned of PLANOUT

plan_gui_bedarf

plan_gui_x_bedarf_zoom50

Displays the nominal capacity of the resource

plan_gui_Ressour

Shows the process used on the resources

plan_gui_Status

plan_gui_x_status_zoom50

Der aktuelle Status den das Projekt trägt

plan_gui_verantwo

plan_gui_x_verantwo_zoom50

Indicates the person responsible for the projects / events.

plan_gui_Ist

Here are the dates of the actual project progress displayed.

plan_gui_Plan

Represents the data of the planned project progress.

plan_gui_datum

Displays the date the project started and the expected end.

plan_gui_Kategorie

plan_gui_x_kategorie_zoom50

Shows as defined in the project / process the performanced Category.

plan_gui_bedarf_kum

plan_gui_x_bedarf_kum_zoom65

Has the same effect as "necessary", but here the need is added and result is written to the parent process and projects.