Of course, a created project, no matter how and where, can be reloaded in the two views. Also here are the steps to open project very similar and are summarized.

 

Planning view

To load in the planning view a project, you do not have to open directly but must add it back to the Planning view. Here, too, it does not matter whether the schedule view is empty or already contains other projects, the project must not be opened already. Now, change in the planning view to "Insert" menu and then the menu item "existing project". This will open the project selection dialog.



Project view

If the project shall be loaded into its project view is, do this with the menu "File" and "Open Project" the menu item. PLANOUT closes the current view and opens a blank project view, about the same time opens the following project selection dialog.

 

Zum Vergrößern klicken.
The project selection dialog

 

 

After the selection and pressing OK, the project is loaded into the corresponding view and displayed.

 

Planning view

Zum Vergrößern klicken.
The plan view with the added project

 

Project view

Zum Vergrößern klicken.
The project view with the loaded project