Here you can change the properties of the shortcut. A link can consider various buffer times and arrange the procedure relative to predecessor or successor.
The general section
The connection specifies the manner of linking individual events.
Minimum distance sets whether the affiliated transactions between a minimum distance or a buffer time should be taken in account. The disclosure can be adjusted in operating days, hours, calendar days, minutes, or percentage.
The implication allows a dependency between two related processes. This feature allows an operation to "Started" as soon as the previous procedure has been changed to "Completed". The prerequisite is that the processes involved "Approved" status have.
In the screenshot below you can see that process 1 is currently being processed (status "Started") and that it has a link to process 2.
Implication before the change of status
In the meantime, the status of process 1 has been set to Stopped by implication to what result that process 2 is automatically changed to Started, since there is a dependency (implication) was registered.
Implication after the change of status